Volkswagen

Volkswagen
Volkswagen
Volkswagen
Germany
Volkswagen
Hannover Logistics Centre

Space to

grow

The first unit was completed after five months. The state-of-the-art facility which spans an area of 83,000 m² guarantees the JIS/JIT conveyor belt supply for the production of the Amarok model. 
Goodman also applies high standards in the sustainable design of the building. A photovoltaic system was installed on the roof for solar energy. Loading and unloading tunnels all around the facility allow it to be operated at low emission levels.

 

Accessibility
  • Direct access to the A2 and A352 motorways
  • Excellent connection to the airports and the Nordhafen (North Harbour) region of Hanover

Delivery time
  • Project duration: 7 months
  • Start of construction: September 2011
  • Delivery: April 2012
Technical specifications
  • Total land area: 83,000 sqm
  • Warehouse and logistics area: 45,000 sqm
  • Office space: 1,000 sqm
  • Overhead doors: 30
  • Loading docks: 4 (optionally 6)
  • Free height: 10 m